Handling machine planning
Introduction
Machine planning is the process of
allocating the requirements for machine hours which can derive from transactions
such as sales orders, internal use, and production orders to available capacity
of machine hours. The requirements can also be based on an MRP scenario which is
generated at the MRP engine via Manufacturing/Planning/MRP engine.
You
can plan machine hours based on the availability and requirements for machines
at Manufacturing/Planning/Machine planning. The machine hour capacity or
availability is based on the generation of capacity in the machine item
maintenance under the Planning tab of machine maintenance via
Manufacturing/Setup/Machines.
Description
At
Manufacturing/Planning/Machine planning, you can filter the machine hours and
requirements planning that you want to display. Define one or more of the filter
criteria and click Refresh to display the machine hours and requirements.
The machine hours and requirements that match the filter criteria you have
specified are then displayed.
Machine hours section
Show /
Hide
Click Show
/Hide to hide or show the Tasks / Requirements section.
Advanced
Click Advanced to define
more criteria and display the machine hours planning for the selected project,
machine, assortment, and/or activity. The following will be available:
- Project
- Click Select to select one
or more project(s). You can select a project by double-clicking the project or
select the project and click Select. To select more than one project,
hold down CTRL and click the projects that you want. A green check mark is then
displayed at the selected project’s Select column. To clear the
selection, click Deselect all. Click Close to exit.
- Note: The steps above apply to
Machine,
Assortment, and
Activity
too.
- Select - Click Select after making a
selection on Project, Machine, Assortment and/or
Activity.
- Close
- Click Close to exit.
Asset group
Type or select an asset group to
display the machine hours planning for machines belonging to the selected asset
group.
Cost center
Type or select a cost center to
display the machine hours planning for machines belonging to the selected cost
center.
Date – to
Type or select a range of dates to
display the machine hours planning within the selected range of dates.
Show: Weekend
Select the Weekend check
box to display machine hours planning during weekends.
Show: Actual
Select the Actual check box
to display actual machines hours that are realized.
Scale
Click - or + to view
the machine hours planning Daily, Weekly, Monthly, or
Yearly.
Overview section
The machine hours that match the
criteria that you have specified are then displayed. Click + at the top left to display the capacity of machine hours for all
displayed machine item. Click + at specific rows to display the capacity of the machine hours for
the respective machine item by respective dates.
Tasks / Requirements
section
Show /
Hide
Click Show / Hide to hide or show the
Machine hours section.
Advanced
Click Advanced to define
more criteria and display the tasks/requirements such as production orders for
the selected warehouse, machine, assortment, activity, and project. The following will be available:
- Filter section
- Warehouse
- Click Select to select the
warehouse(s) to display the tasks/requirements for the selected warehouse(s).
Select a warehouse by double-clicking the warehouse or select the warehouse and
click Select. To select more than one warehouse, hold down CTRL and click
the warehouses that you want. A green check mark is then displayed at the
selected warehouse’s Select column. To clear the selection, click
Deselect all. Click Close to exit. These steps apply to
Machine,
Assortment,
Activity, and
Project.
- Show:
Planned - Select the Show: Planned
check box to display the already planned tasks/requirements.
- Based on
scenario - Select the Based on
scenario check box to display the requirements based on an MRP scenario.
This enables the Scenario: MRP option. Note that selecting this check box will
disable the Machine and Project filters, and the
Transactions section.
- Scenario:
MRP - Type or select an MRP scenario to
display the requirements based on the selected MRP scenario.
- Projects
section
- Make
items - Select the Make items check
box to display the Make item column showing item code and item
description of the requirements.
- Customers - Select the Customers check
box to display the Customers column showing the customer account of the
requirements such as for sales orders.
- Transactions section
- Sales orders/Internal
use/Production orders - Select Not authorized to display sales
orders, internal use and/or production orders that are not authorized. Select
Authorized to
display sales orders, internal use, and/or production orders that are
authorized. Click Select to activate
the relevant Selection
codes to display sales orders, internal use and/or production
orders that belongs to the activated selection codes. If you have selected the Based
on scenario check box, this section will be disabled.
- Select - Click Select to save the
advanced selections.
- Close - Click Close to exit.
Cost center
Type or select a cost center to
display the requirements from the selected cost center.
Date – to
Type or select a range of dates to
display the requirements within the selected date range.
Overview
section
The requirements such as sales
orders, production orders or internal use that match the criteria you have
specified are then displayed. Click to
display the capacity of machine hours for all machine items by items, projects,
or requests. Select Items to display the machine hour capacity by machine
item. Select Projects to display the machine hour capacity by projects.
Select Request to display the machine hour capacity by
requests.
Click + on specific rows to display the requirements orders for the respective
machine hours by the respective dates.
At the bottom of the Machine:
Planning screen, there is a legend which indicates the status of the machine
hour planning for each date column.
Not
Planned
A column with this color indicates
that the machine hour is not planned.
Incomplete
Planned
A column with this color indicates
that the machine hour is partly planned. The machine hour which is partly
planned is split in 2 cells; one which is planned machine hour shown in green
cell and the other not planned machine hour shown in yellow
cell.
Planned
A column with this color indicates
that the machine hour is planned.
Below the legend is the indication
of the planning date that has been selected for allocation.
Date from
To
This displays the date range of
planning allocation selected at the Tasks / Requirements
section.
Quantity
This displays the required
quantity of hours selected at the Tasks / Requirements section. This
quantity is as per the selected machine hour requirement cell under the Tasks
/ Requirements section.
Machine
This displays the machine hour
item selected at the Machine hours section. This machine hour item is as
per the selected cell of the machine hour under the Machine hours section.
Buttons
Refresh
Click Refresh to display
the machine hours and requirements planning based on the specified criteria.
Details
Click Details to display
the detailed information of the machine hour requirements. In Details,
click Full level to display the source breakdown of the machine hour
requirements.
Plan
Click Plan to allocate the
available machine hours to the selected requirement.
Note: To enable the Plan button, select the available
capacity of machine hour and the machine hour requirement.
Delete
Click Delete to delete the
already planned (allocated) machine hour.
Note: The Delete button is
enabled if you select an already planned (allocated) machine hour.
Close
Click Close to exit.
Related
documents
Main Category: |
Attachments & notes |
Document Type: |
Online help main |
Category: |
|
Security level: |
All - 0 |
Sub category: |
|
Document ID: |
13.197.339 |
Assortment: |
Exact Globe+
|
Date: |
26-09-2022 |
Release: |
|
Attachment: |
|
Disclaimer |